Issue 2 · 18 September 2026 · 5 min read
Solar submissions fell to 4GWp. Construction jumped.
Plus the NAO's £7.8bn grid delay warning, Enerparc's insolvency filing and everything else worth knowing this week.
The big one
UK solar construction jumps by 1GWp in Q3 as firm connection dates unlock the pipeline
Solar Media’s Josh Cornes has weighed up the year so far and his analysis is likely to bring some relief to the UK solar supply chain. Construction starts had slowed to just 1.8GWp between July 2025 and April 2026, as developers held back without firm grid connection dates, a slowdown many with their eye on the ball will have seen coming, and one that makes this quarter's pickup all the more welcome.
Construction accelerated sharply in Q3 2026, with 1GWp of UK solar starting build once developers finally received firm 2027 grid connection dates, with 4.7GWp now under construction overall. The rebound comes even as planning submissions have slowed: only 4GWp has been submitted so far this year, down from 12.5GWp at the same point in 2025, with 2.7GWp of that in NSIPs.
Approvals are holding up better: 7.5GWp across just over 100 sites, against 9.1GWp across more than 180 last year. Average determination time for projects above 5MWp at local planning authority level has hit 60 weeks, up from 51 in 2025. The refusal rate at LPA level still hovers around 23-25%.
CfDs still back 65% of assets entering construction since the start of 2023. But 15 projects have terminated theirs, four of them under construction and one operational. Severn Trent, Liberty Global and Atrato have all stated a preference for CPPAs over CfDs.
Over 100 assets totalling 6.2GWp have changed hands this year, and most transmission-connected projects with Gate 2 Phase 1 notifications still haven't received firm connection dates, a bottleneck that could stall the next wave once the current backlog of 2027 slots clears.
Firm 2027 connection dates have already triggered a scramble for EPC contracts and equipment, and most 2028 projects are still waiting on dates of their own. When those do land, expect the same rush to hit supply chains all over again, so lock in your positions now rather than compete for capacity once the next wave breaks.
Not to be ignored
NAO puts a £7.8bn a year price on grid upgrade delays
The National Audit Office says constraint payments will add £7.8bn a year to bills by 2030 under current plans. Do nothing and it hits £12.7bn; accelerate everything and it still lands between £2.8bn and £3.6bn. Constraint costs have already climbed from £0.6bn in 2018-19 to £1.9bn in 2025-26. Of the 80 grid projects NESO identified in its 2024 Clean Power advice, 64 are ongoing, but most are still early stage and unlikely to meet NESO's optimal connection dates.
Why it matters: Expect connect-and-manage itself to come under increasing political pressure as billpayers keep absorbing costs the network, not developers, is creating.
Report puts UK commercial rooftop solar potential at 60GW
New research commissioned by Real Estate:UK, authored by Cushman & Wakefield, finds more than 90% of suitable UK commercial roof space unused: over 60GW of potential against an estimated 3-5GW in use.
Industrial and logistics are flagged as particularly untapped. On a typical 300kWp system costing £250,000, the report models a 20% first-year net yield and 5.5-year payback if tenant-funded, 12% and eight years if landlord-funded.
Why it matters: Watch for any movement on the report's seven policy asks, particularly clarity on REIT rules for solar and any move to lift the 50kW permitted development cap.
Enerparc's insolvency is a warning sign for European solar's new reality
German developer Enerparc filed for insolvency this week, months after securing a billion-euro refinancing package. Sister company Pvwerk followed days later; both say operations continue as normal while insolvency experts assist restructuring.
S&P Global's Josefin Berg called it "an earthquake". Rystad's Vegard Vollset says pure-play solar development is essentially finished in Europe, with too much capacity deployed at the same hours depressing prices.
Why it matters: Consolidation looks likely as utilities pick up distressed portfolios at a discount, so treat any pure-play solar developer counterparty as carrying real credit risk right now.
Invinity reconsiders UK expansion after LDES shortlist leans lithium-ion
Ofgem's provisional cap-and-floor shortlist, published in June, covers 16 long-duration storage projects totalling 7.6GW. Only one uses vanadium flow batteries: Frontier Legacy in North Wales. According to a Times report, Invinity CEO Jonathan Marren said the UK-based vanadium flow manufacturer will need to reconsider its UK operations and may focus more on Europe and the US, though the company says existing UK manufacturing capacity is not being withdrawn.
Marren said the shortlist "appears misaligned with the government's broader ambitions around reindustrialisation." Most of the shortlisted projects use lithium-ion technology, largely manufactured in China.
Why it matters: How Ofgem scores this final round could shape whether domestic manufacturing gets a real foothold in UK long-duration storage.
Of note
Lincolnshire councillors object to 750MW Meridian solar farm
The county council's planning committee agreed on 7 September to recommend refusal of Meridian Solar Farm Limited's 1,616-hectare, 40-year DCO north of Crowland and east of Spalding, with members questioning whether the scheme is deliverable given it relies on a not-yet-built Weston Marsh Substation B and a fresh set of pylons; the Secretary of State has the final say.
Pexapark: European PPA prices up 2.2% in August
European renewable PPAs averaged €46.02/MWh in August, up 2.2% on July, with Great Britain's 4.9% month-on-month rise the largest in Europe. Pexapark attributes some of that to its own recalibration of GB PPA fair values, which found offtakers had moderated the risk discounts embedded in their pricing, with ten-year PPAs seeing an average increase of £5/MWh.
120 organisations ask the Government to take levies off electricity bills
A letter coordinated by Energy UK and E3G's Electricity Bills Taskforce, signed by over 120 utilities, trade associations, consumer groups and other stakeholders wants all policy levies moved off residential and commercial electricity bills into general taxation at the Autumn Budget, which it says would cut business energy bills by up to 20%.
2026 will be a record year for UK rooftop solar, says Solar Energy UK
MCS has logged 207,619 certified small-scale installations so far this year, already past the previous high of 203,697 that stood from 2011 to 2025 but still behind 2025's own total of 269,195. Solar Energy UK says the current pace puts 300,000 within reach by year-end, which would make 2026 the first year to pass that mark. Government data shows solar on 55,773 new-build English homes in H1, 58% of the total.
Elsewhere this week
Massive Dover solar farm set for approval
Council's £1.9 billion renewable investments listed despite claims climate change is not man made
BYD launches 62 MWh GC Block for gigawatt-scale battery storage plants
Morecambe offshore wind farm receives development consent for transmission assets
Aura Power starts Grimsby solar operations
More than 500 jobs to be created at 22 new Scottish energy projects
One thing I'm watching: Ofgem's final cap-and-floor decision, and whether the vanadium flow share of the list moves at all from one project. I won't hold my breath.
That's Current State. See you next Friday at 10am.

Was this useful?
Get the next issue
This issue is checked for accuracy at the time of writing, but source articles may be updated after review.