Issue 10 · 13 November 2026 · 7 min read
Botley West had critical national priority status. It still lost.
Plus RWE and KKR's £12bn Vanguard deal, Watt-Logic on NESO's margin notice and everything else worth knowing this week.
The big one
Botley West refused, and critical national priority status didn't carry it
The government has refused development consent for Botley West, an 840MW solar farm in West Oxfordshire, in a decision letter dated 10 November. Minister Curran took the decision for the Energy Secretary, following the Examining Authority's recommendation to refuse. The examiners had also said there may be a case for consent if certain matters were resolved, but the minister followed their main recommendation.
The applicant's own figure puts 69% of the site in Green Belt, and the minister found no very special circumstances to outweigh the harm. Harm to Blenheim Palace World Heritage Site is judged less than substantial, but heritage still weighs substantially against the scheme. London Oxford Airport, which the examiners describe as England's biggest pilot-training airport, is left with residual aviation impacts the letter describes as "a real, credible and significant risk to public safety". Best and most versatile land makes up 42% of the installation area, around 314 hectares, with no specific commitment to return soil to at least its pre-construction grade.
Under EN-1, the Overarching National Policy Statement for Energy, the scheme counts as critical national priority (CNP) infrastructure. Where the CNP presumptions apply, the starting point is that very special circumstances exist to justify building. Need still carried substantial positive weight. But the minister agrees with the examiners that the developer treated the impacts as inevitable and acceptable because of that status, rather than avoiding or reducing them early in design. With the mitigation hierarchy not properly applied, those presumptions were off the table.
CNP status is a presumption a scheme has to earn through its design, not cover for harms it could have avoided. If you have a DCO in preparation, have your planning team show, topic by topic, where each impact was avoided or reduced before it was mitigated, because that record decides whether the presumption applies at all.
Not to be ignored
RWE and KKR close £12bn Vanguard financing, with 35 banks and the National Wealth Fund
RWE and KKR have reached financial close on Vanguard West and Vanguard East, two 1.4GW offshore wind projects 50 to 80km off the Norfolk coast. Total investment, transmission included, is around £12bn. KKR has completed its purchase of a 50% stake in each project, first announced in January, and RWE leads delivery.
The non-recourse debt is £11.1bn of cash facilities plus £1.7bn of ancillary facilities from 35 international banks, which RWE calls the biggest project financing UK offshore wind has seen. It includes £1bn from the National Wealth Fund, and Germany's Euler Hermes and Denmark's EIFO provided credit cover. Both projects hold 20-year, inflation-indexed AR7 CfDs at £91.20/MWh in 2024 prices. Offshore construction is set to start in early 2027, with full commissioning expected in 2030.
Why it matters: This is the first time the National Wealth Fund has joined a UK offshore wind project financing, and a public lender taking £1bn of the debt makes a syndicate easier to fill. If you are raising debt for a contracted UK solar or storage project, ask your adviser whether NWF could anchor it, before you start sounding out commercial banks.
Metlen agrees to sell 119MW of UK solar to Nala, a first-time UK buyer
Metlen Energy and Metals has signed sale and purchase agreements with Nala Renewables for a 119MW portfolio of four utility-scale UK solar sites. Project specifics were not disclosed. Every project is ready-to-build or under construction, with delivery phased across 2027 and 2028, and Metlen has secured a mix of PPAs and CfDs for them.
The deal is Nala's entry into the UK, and both sides describe it as the basis of a long-term partnership. Metlen runs an asset rotation model: it develops and builds plants, sells them, and puts the proceeds back into its international pipeline. Solar Media Market Research says the sites' SPVs have not yet changed hands. Nala's interim CEO, Remy Verot, says the UK has been a priority market for it to enter at the right time.
Why it matters: A new owner in UK solar means new doors to knock on. Nala will need O&M, asset management and other services as these sites are delivered, so if you sell to solar owners, get in front of it before its UK supply chain is set. If you're looking to sell a portfolio, it's also a new name to approach.
Five EU leaders want the UK to pay into cohesion funds for electricity market access
The leaders of Belgium, Germany, Denmark, Luxembourg and the Netherlands have written to the presidents of the European Commission and European Council, asking that UK integration into the EU electricity market be tied to a UK financial contribution to EU cohesion funds. Euronews has seen a draft joint EU-UK statement suggesting EU leaders broadly back the principle, though the text could change before the summit on 20 November.
Negotiations on integration are already under way. Energy minister Martin McCluskey has said no amount or contribution has been agreed, and that any payment would have to deliver value for money for Britain. Norway, part of the internal market through the EEA, puts roughly €391m a year into cohesion grants. The letter frames a deal around North Sea ambitions of up to 100GW of joint projects and 300GW of offshore wind.
Why it matters: A UK payment for market access is now an open negotiating point, with an answer possible on 20 November. If your revenue case leans on interconnector flows or GB to EU price spreads, flag it to your investors as an assumption still in play.
Watt-Logic questions why NESO's 9 November margin notice covered the morning, not the evening
NESO issued an Electricity Margin Notice on Sunday evening for 6am to 11am on Monday 9 November, the first for a morning rather than an evening, writes Kathryn Porter at Watt-Logic. The forecast shortfall of 1,388MW fell to 200MW and the notice was cancelled soon after 9am. No warning came for the evening, when residual load was much higher and the system price reached £755/MWh.
Porter suggests battery modelling may explain it. Britain has 8.7GW of batteries installed. Notified battery output dropped to around 200MW from 9am, and NESO's instructions had the fleet charging between 9am and 11am. In her view, the batteries that made the evening look well covered were largely the same ones on hand that morning, simply scheduled for later. Modo Energy figures show NESO accepted 7% of in-merit battery offer volume in October, against 15% a year earlier.
Why it matters: The battery fleet is there, but NESO's systems may not be using it well when margins are tight. If you own or optimise BESS, press NESO and your trade body on the battery reporting in generation-by-fuel data, which was planned for April and still is not live, because the fleet needs to be visible before it can be counted on.
Of note
Karpowership's Kinetics Energies buys the consented 100MWh Kitwell BESS near Birmingham
Kinetics Energies, part of Turkish energy group Karpowership, has bought Kitwell, a fully consented 50MW/100MWh battery site near Birmingham, from Anglo Renewables. The price was not disclosed, and the project is expected to connect to the grid in 2028. Mehmet Katmer, CEO of Kinetics Energies, says it fits a strategy to deliver 800MW of low and zero carbon assets across Europe.
Councils lose High Court bid against 800MW Springwell
A challenge by Lincolnshire County Council and North Kesteven District Council to the approval of Springwell, the 800MW solar farm from EDF power solutions and Luminous Energy, has been rejected and will not go to a full hearing. The councils argued ministers had failed to properly consider the impact on rural villages and landscape, or the combined effect of similar schemes nearby. One campaigner, Marianne Overton, points to the National Grid substation proposed at Navenby, which the farm would rely on.
SSEN Transmission has invested around £8bn in northern Scotland's grid since 2020
SSEN Transmission, SSE's electricity transmission business, has put around £8bn into upgrading the north of Scotland's grid since 2020. Over the same period, renewable generation connected to that network rose from around 6.3GW to 10.8GW. SSE is backing COP31's pledge to lift electricity to 35% of final energy use by 2035, and SSEN Transmission estimates its investment, part of a £29bn Pathway to 2030 programme, could support up to 50,000 UK jobs.
Land access is an under-discussed barrier for renewables, argues Shakespeare Martineau's Stephen Scott
Stephen Scott, a real estate disputes partner at Shakespeare Martineau, argues the UK has the land in principle, but that renewables now compete for it with housing, food production and biodiversity schemes. He points to grid capacity, inheritance tax relief rules that may make farmers wary of diversifying, and Biodiversity Net Gain requirements. He wants a strategic land-use framework and more resource for planning departments.
Elsewhere this week
Ofgem consults on BSC changes for the new code governance regime, closing 18 December
Capacity Market technology review adds no new class, with the next open letter due autumn 2027
Eastern Green Link 2 marks two years of construction, with full energisation expected in 2029
One thing I'm watching: Whether the 20 November EU-UK summit puts a figure, or a formula, on a UK payment for electricity market access.
That's Current State. See you next Friday at 10am.